Lane Closures on Miller coming this week
/
Notice of Temporary Traffic Control Plan
MILLER AVENUE – MAIN TO CHAPIN
March 4 – March 12, 2010
Location and Limits of Affected Area:
Miller Avenue from North First Street to Chapin Street.
Description of Work:
Storm and sanitary sewers are being cleaned and videotaped.
Temporary Construction Traffic Control Plan:
Beginning March 4, Miller Avenue between Main Street and First Street will be reduced to one lane, with eastbound traffic being maintained. Westbound traffic at First Street will be detoured south to Huron Street, west on Huron Street, and north on Seventh Street, back to Miller Avenue.
During this work the traffic may experience brief delays within the areas influenced by this work. Detour signs will be posted for this construction; however the motorists are advised to seek alternate routes. To maintain the safety of all, please reduce speeds and drive cautiously through work zones. We thank you in advance for your patience as these necessary public infrastructure improvements are completed.
Project Contacts:
City of Ann Arbor
Nick Hutchinson, P.E., Project Engineer (734) 845-0698
Adam Ajam, Civil Engineering Specialist, (734) 323-6565
DownUnder Construction
Danny Butterfield, Construction Contractor, (269) 377-1944
MILLER AVENUE – MAIN TO CHAPIN
March 4 – March 12, 2010
Location and Limits of Affected Area:
Miller Avenue from North First Street to Chapin Street.
Description of Work:
Storm and sanitary sewers are being cleaned and videotaped.
Temporary Construction Traffic Control Plan:
Beginning March 4, Miller Avenue between Main Street and First Street will be reduced to one lane, with eastbound traffic being maintained. Westbound traffic at First Street will be detoured south to Huron Street, west on Huron Street, and north on Seventh Street, back to Miller Avenue.
During this work the traffic may experience brief delays within the areas influenced by this work. Detour signs will be posted for this construction; however the motorists are advised to seek alternate routes. To maintain the safety of all, please reduce speeds and drive cautiously through work zones. We thank you in advance for your patience as these necessary public infrastructure improvements are completed.
Project Contacts:
City of Ann Arbor
Nick Hutchinson, P.E., Project Engineer (734) 845-0698
Adam Ajam, Civil Engineering Specialist, (734) 323-6565
DownUnder Construction
Danny Butterfield, Construction Contractor, (269) 377-1944