East Stadium Traffic Control Update
/
Notice of Updated Temporary Traffic Control Plan from the City of Ann ArborE. Stadium Improvement Project-Phase IA
June 18, 2012 to July 9, 2012
Location and Limits of Affected Area:E. Stadium Blvd. between Packard Road and Brockman Blvd.
June 18, 2012 to July 9, 2012
Location and Limits of Affected Area:E. Stadium Blvd. between Packard Road and Brockman Blvd.
Description of Work:
The E. Stadium Improvement Project includes the installation of new 8-inch water mains on north and south sides of the street between Packard and Brockman and resurfacing of the E. Stadium Blvd. from Packard Rd. to Washtenaw Ave. The construction includes four major phases, where Phase I includes the installation of the new water main along the north side of E. Stadium Blvd. between Packard and Brockman, Phase II includes the installation of the new water main along the south side of E. Stadium Blvd. between Packard and Brockman, and Phases III and IV will resurface the pavement along the north and south sides of E. Stadium Between Brockman and Washtenaw
Updated Temporary Construction Traffic Control Plan:
This notification adds a sub-phase to the Phase I traffic control already in effect on E. Stadium Blvd. Phase IA is scheduled to begin on Monday June 18, 2012, after the end of 2012 school year. With the Phase IA traffic control, the southbound traffic on Brockman Blvd. between the Shadford Rd. and E. Stadium Blvd will be directed west on Shadford Rd. and then south on Harding Rd. to E. Stadium Blvd. Pedestrian traffic will be maintained during this phase of construction.