Traffic Control Plan and Update for E. Stadium Bridges and State St.

E. Stadium Boulevard Bridges Replacement Project
August 11, 2012

Location and Limits of Affected Area:
E. Stadium Boulevard from Kipke Drive to S. Industrial Highway
S. State Street from Stimson to Granger Avenue

Description of Work:
Hot mix asphalt paving on S. State Street.

Temporary Construction Traffic Control Plan:

August 11, 2012 – August 12, 2012 (Northbound S. State Street)
Northbound S. State Street will be temporarily closed to vehicular traffic from Stimson to Granger Avenue. A detour route will be posted.

Southbound S. State Street vehicular traffic will be maintained at all times.

All vehicular traffic on S. State Street will return to its normal configuration at the end of the work day on August 12, 2012.

E. Stadium Boulevard between Kipke Drive and S. Industrial Highway will remain closed to pedestrian and vehicular traffic until November 14, 2012 to allow for the removal and replacement of the E. Stadium Boulevard bridges over the Ann Arbor Railroad and S. State Street. Vehicular and pedestrian detour routes are in place.

We thank you in advance for your patience as these necessary public infrastructure improvements are completed.